Risks

A risk is any threat of an event that may have a negative impact to the project, and which may be neutralized, or at least minimized, through pre-defined actions.

The risk management plan is a key point to project management :

  • Identify risks and estimate their severity and likelihood.

  • Identify mitigating actions.

  • Identify opportunities.

  • Follow-up actions.

  • Identify risks that finally occur (becoming an issue).

Contingency reserve

  • Contingency reserve is defined according to monetary impact and likelihood of occurrence.

  • Contingency reserve for risks and potential gain for opportunities allow to define the project reserve. (See: Project reserve)

Monitoring indicator

  • Possibility to define indicators to follow the respect of dates values.

Respect of initial due date
Respect of planned due date

Section Description

Required fields Required File legend

Field

Description

Id

Unique Id for the risk.

Required File Name

Short description of the risk.

Required File Type

Type of risk.

Required File Project

The project concerned by the risk.

Severity

Level of importance of the impact for the project.

Likelihood

Probability level of the risk to occur.

Criticality

Global evaluation level of the risk.

Cost of impact

Impact cost of the risk.

Project reserved cost

The reserve amount according to the risk likelihood.

Origin

Element which is the origin of the risk.

Cause

Description of the event that may trigger the risk.

Impact

Description of the estimated impact on the project if the risk occurs.

Description

Complete description of the risk.

Section Treatment

Required fields Required File legend

Field

Description

Required File Status

Actual status of the risk.

Responsible

Resource who is responsible for the treatment of the risk.

Priority

Expected priority to take into account this risk.

Initial end date

Initially expected end date of the risk.

Planned end date

Updated end date of the risk.

In progress

Flag to indicate that risk is taken into account.

Done

Flag to indicate that risk has been treated.

Closed

Flag to indicate that risk is archived.

Cancelled

Flag to indicate that risk is cancelled.

Result

Complete description of the treatment done on the risk.

Opportunities

An opportunity can be seen as a positive risk. It is not a threat but the opportunity to have a positive impact to the project.

Potential gain

  • The potential gain is defined according to the expected amount and likelihood of occurrence.

  • Contingency reserve for risks and potential gain for opportunities allow to define the project reserve.

  • See: Project reserve

Section Description

Required fields Required File legend

Field

Description

Id

Unique Id for the opportunity.

Required File Name

Short description of the opportunity.

Required File Type

Type of opportunity.

Required File Project

The project concerned by the opportunity.

Significance

Level of importance of the impact for the project.

Likelihood

Evaluation of the estimated improvement, or positive impact, on the project of the opportunity.

Criticality

Global evaluation level of the opportunity.

Expected improvement

Expected amount of the opportunity.

Project reserved gain

The estimated gain, according to the opportunity likelihood.

Origin

Element which is the origin of the opportunity.

Opportunity source

Description of the event that may trigger the opportunity.

Impact

Description of the estimated positive impact on the project.

Description

Complete description of the opportunity.

Section Treatment

Required fields Required File legend

Field

Description

Required File Status

Actual status of the opportunity.

Responsible

Resource who is responsible for the opportunity.

Priority

Expected priority to take into account this opportunity.

Initial end date

Initially expected end date of the opportunity.

Planned end date

Updated end date of the opportunity.

In progress

Flag to indicate that opportunity is taken into account.

Done

Flag to indicate that opportunity has been treated.

Closed

Flag to indicate that opportunity is archived.

Cancelled

Flag to indicate that opportunity is cancelled.

Result

Complete description of the treatment of the opportunity.

Criticality value calculation

Criticality value is automatically calculated from Severity (Significance) and Likelihood values.

Criticality, Severity (Significance) and Likelihood values are defined in lists of values screens.

See: Criticalities, Severities and Likelihoods screens.

In the previous screens, a name of value is set with numeric value.

Criticality numeric value is determined by a simple equation as follows:

Default values

  • Default values are determined.

  • You can change its values while respecting the equation defined above.

Issues

An issue is a problem that occurs during the project.

If the risk Management plan has been correctly managed, issues should always be occurring identified risks.

Actions must be defined to solve the issue.

Monitoring indicator

  • Possibility to define indicators to follow the respect of dates values.

Respect of initial due date
Respect of planned due date

Section Description

Required fields Required File legend

Field

Description

Id

Unique Id for the issue.

Required File Name

Short description of the issue.

Required File Type

Type of issue.

Required File Project

The project concerned by the issue.

Criticality

Level of importance of the impact for the project.

Priority

Priority requested to the treatment of the issue.

Origin

Element which is the origin of the issue.

Cause

Description of the event that led to the issue.

Impact

Description of the impact of the issue on the project.

Description

Complete description of the issue.

Section Treatment

Required fields Required File legend

Field

Description

Required File Status

Actual status of the issue.

Responsible

Resource who is responsible for the issue.

Initial end date

Initially expected end date of the issue.

Planned end date

Updated end date of the issue.

In progress

Flag to indicate that issue is taken into account.

Done

Flag to indicate that issue has been treated.

Closed

Flag to indicate that issue is archived.

Cancelled

Flag to indicate that issue is cancelled.

Result

Complete description of the treatment of the issue.

Actions

An action is a task or activity that is set-up in order to :

  • Reduce the likelihood of a risk

  • or reduce the impact of a risk

  • or solve an issue

  • or build a post-meeting action plan

  • or just define a “to do list”.

The actions are the main activities of the risk management plan.

They must be regularly followed-up.

Private action

  • Private actions allow to manage a personal to-do list.

Monitoring indicator

  • Possibility to define indicators to follow the respect of dates values.

Respect of initial due date
Respect of planned due date

Section Description

Required fields Required File legend

Field

Description

Id

Unique Id for the action.

Required File Name

Short description of the action.

Required File Action type

Type of action.

Required File Project

The project concerned by the action.

Priority

Priority requested to the treatment of the action.

Private

Box checked allows to define a private action.

Description

Complete description of the action.

Section Treatment

Required fields Required File legend

Field

Description

Required File Status

Actual status of the action.

Responsible

Resource who is responsible for the action.

Initial due date

Initially expected end date of the action.

Planned due date

Updated end date of the action.

In progress

Box checked indicates that the action is taken over.

Done

Box checked indicates that the action has been treated.

Closed

Box checked indicates that the action is archived.

Cancelled

Box checked indicates that the action is cancelled.

Efficiency

Evaluation of the efficiency the action had on the objective (for instance on the risk mitigation).

Result

Complete description of the treatment of the action.